The ELTA Payment Stages at a Glance
Because ELTA is still being built, its homes are paid for under the normal progressive payment scheme, in portions that keep pace with construction. The 5% booking fee is paid when the option to purchase is granted, 15% is due at the sale and purchase agreement within eight weeks, and the last 80% is released stage by stage as the works advance, up to the Certificate of Statutory Completion.
The Housing Developers Rules fix the stages and each one’s percentage, so a one-bedroom-and-study home and a five-bedroom home at ELTA follow the same schedule. The table’s last column gives the running total paid by each stage.
| Stage | % of price | Cumulative |
|---|---|---|
| Booking fee, on the grant of the option to purchase | 5% | 5% |
| Sale and purchase agreement, within 8 weeks | 15% | 20% |
| Completion of foundation | 10% | 30% |
| Completion of reinforced concrete framework | 10% | 40% |
| Completion of partition walls | 5% | 45% |
| Completion of roofing and ceiling | 5% | 50% |
| Completion of doors, windows, electrical wiring and plumbing | 5% | 55% |
| Completion of car park, roads and drains | 5% | 60% |
| Temporary Occupation Permit (TOP) | 25% | 85% |
| Certificate of Statutory Completion | 15% | 100% |
Standard schedule for a building under construction under the Housing Developers Rules, as at October 2026.
Paying the First 20 Percent at ELTA
Before any construction instalment begins, the buyer funds the first 20% personally. The 5% booking fee goes in cash at the grant of the option, and the 15% due at the sale and purchase agreement is paid no more than eight weeks later.
Stamp duty runs alongside these two payments but is billed on its own. Buyer’s Stamp Duty, together with any Additional Buyer’s Stamp Duty, must be paid within 14 days of the sale and purchase agreement being signed, which places it early in the budget next to the booking fee. Current rates appear on the ELTA stamp duty page.
Cash, CPF and the Bank Loan at ELTA
MAS rules govern how the buyer’s share splits between cash and CPF. With no existing housing loan, a buyer can borrow up to 75% of the price. Of the 25% paid first, at least 5% must be cash, which the booking fee already meets, and the other 20% can come from cash or CPF Ordinary Account savings, within CPF limits.
Take a 75% loan. The booking fee and the agreement payment make up 20%; half of the 10% foundation instalment brings the buyer’s contribution to 25%, and the bank pays every certified stage after that. A borrower who already has a housing loan, or who falls into the lower band, gets a smaller loan limit and puts in a larger share in cash.
| Borrower | Max loan | Own funds | Minimum cash |
|---|---|---|---|
| No outstanding housing loan | 75% | 25% | 5% |
| No outstanding loan, tenure over 30 years or past age 65 | 55% | 45% | 10% |
| One outstanding housing loan | 45% | 55% | 25% |
| Two or more outstanding housing loans | 35% | 65% | 25% |
Source: MAS, checked 20 October 2026. Limits can change; confirm with MAS or your bank before signing.
How the Loan Is Drawn During ELTA Construction
As each stage is certified, the developer issues a notice and the bank settles that instalment. During construction, interest accrues only on the sums drawn so far. Monthly repayments are therefore modest at first and grow as the two 39-storey towers progress from the foundation to the roof and then to the Temporary Occupation Permit.
The biggest single payment is the 25% due at the Temporary Occupation Permit, followed by the closing 15% at the Certificate of Statutory Completion. On the developer’s factsheet, vacant possession is expected by 31 March 2029 and legal completion by 31 March 2032.
Price is not the only cap on the loan; income sets one too. The Total Debt Servicing Ratio (TDSR) requires all monthly debt repayments, including the new loan, to stay within 55% of gross monthly income, with the new loan assessed at a 4% floor or at its thereafter rate, whichever is higher.
Booking at ELTA After the Top-Out
According to EdgeProp in September 2026, structural top-out has been reached on both towers. A buyer who books now therefore pays for the stages already certified on the timetable set out in the sale and purchase agreement, which usually brings a larger amount forward to the start.
For any particular home, the Sales Concierge can confirm which stages have been reached and send its payment schedule together with the price list. Showflat viewings are arranged by appointment through the Sales Concierge.
Planning ELTA Payments with the Calculator
Enter a price, a loan and an interest rate into the ELTA progressive payment calculator and it returns the sum due and an estimated monthly instalment for every stage, opening on an illustrative figure to be replaced with the buyer’s own and a default interest rate of 1.50%. Its schedule also slots in Buyer’s Stamp Duty and any ABSD and divides the buyer’s own share between cash and CPF. The payment scheme page explains each stage further, and the housing loan page covers the loan limits.
This article is general information as at the date shown and is not financial, legal or tax advice. Particulars of ELTA are from the developer’s published documents, statutory figures are as set out on this site’s financing pages, and distances are straight-line measurements on OneMap. Sources: the Housing Developers Rules standard schedule and MAS loan limits as set out on this site’s payment scheme and housing loan pages (checked 20 October 2026); the developer’s factsheet; EdgeProp (17 September 2026).
Talk to the ELTA Sales Concierge
The Sales Concierge sends the price list on request, the homes still available and the e-brochure for ELTA. Showflat viewings are arranged by appointment through the Sales Concierge.