The ELTA Completion Dates in Brief
The developer’s factsheet gives 31 March 2029 as the expected date of vacant possession for ELTA and 31 March 2032 as the expected date of legal completion. Construction is well advanced: EdgeProp reported on 17 September 2026 that both 39-storey towers had reached their structural top-out.
Those two dates frame the rest of the timeline, and the construction stages before them set the payment calendar. The dates that apply to a particular home are the ones written into its sale and purchase agreement.
From the Start of the Lease to the ELTA Launch
The 99-year lease of the site began on 13 February 2024. The site is Lot 05668V of Mukim 3, about 13,451.1 square metres with a gross plot ratio of 3.5, and the factsheet describes two residential blocks of 39 storeys with one basement, a three-storey multi-storey car park, a swimming pool and communal facilities. The developer then prepared the documents that define the development: the briefing slides of 29 November 2024, the floor plans for the thirteen home types dated 23 December 2024, the factsheet of 31 December 2024 with the unit mix of 501 homes, and the e-brochure and unit annexes of 9 January 2025.
EdgeProp reported the preview on 7 February 2025, and the launch followed on 22 February 2025. The table gathers every dated milestone recorded on this site.
| Date | Milestone |
|---|---|
| 13 Feb 2024 | The 99-year lease of the site begins |
| 29 Nov 2024 | The developer’s briefing slides |
| 23 Dec 2024 | Floor plans for the thirteen home types |
| 31 Dec 2024 | Factsheet: 501 homes, expected vacant possession 31 March 2029 |
| 9 Jan 2025 | E-brochure and unit annexes |
| 7 Feb 2025 | Preview (EdgeProp) |
| 22 Feb 2025 | Launch |
| 17 Sep 2026 | Both towers reach structural top-out (EdgeProp) |
| 31 Mar 2029 | Expected vacant possession |
| 31 Mar 2032 | Expected legal completion |
Sources: the developer’s factsheet, e-brochure, floor plans and unit annexes; EdgeProp.
Building ELTA: Method and Team
The towers are built with prefabricated prefinished volumetric construction, known as PPVC, by the main contractor China Construction Realty. P&T Consultants is the architect, TW-Asia Consultants the civil and structural engineer and Rankine & Hill the mechanical and electrical engineer, with Index Design for the interiors, EcoPlan Asia for the landscape and Asia Infrastructure Solutions as quantity surveyor.
The development is targeting BCA Green Mark Platinum Super Low Energy, with solar panels on the roofs, naturally ventilated lobbies and corridors and energy-efficient lifts. The developer, HC Land (Clementi) Pte. Ltd., holds housing developer’s licence C1501 and is a joint venture between MCL Land and CSC Land Group (Singapore). The ELTA developer page introduces the partners and the design team.
How ELTA Construction Stages Link to Payments
Because the homes are sold under construction on the normal progressive payment scheme, the timeline also sets the payment calendar. After the booking fee and the sale and purchase agreement, instalments fall due as each stage is certified: the foundation, the reinforced concrete framework, the partition walls, the roofing and ceiling, the doors, windows, wiring and plumbing, and the car park, roads and drains.
The Temporary Occupation Permit brings a 25% instalment and the Certificate of Statutory Completion the final 15%. With both towers topped out, a home booked now may have several stages already certified, and those instalments fall due on the timetable in the sale and purchase agreement. Interest during construction is charged only on what has been drawn, so loan repayments start low and rise as the works progress. The ELTA payment scheme page lists every stage.
Vacant Possession and Legal Completion at ELTA
The developer’s factsheet and e-brochure give 31 March 2029 for vacant possession; the earlier briefing slides gave the first quarter of 2029, and the exact date from the newer documents is the one used on this site. Legal completion is expected by 31 March 2032, three years later. The 25% instalment at the Temporary Occupation Permit and the final 15% at the Certificate of Statutory Completion are the last two payments before the home is fully paid. Areas on the plans are approximate and subject to final survey, and the sale and purchase agreement governs.
Following the ELTA Timeline from Here
The ELTA latest updates page keeps a dated record of each step, newest first, from the start of the lease and the issue of the developer’s documents to the launch and the top-out, and adds construction milestones as they are reported on the way to vacant possession. It also notes any statutory change to stamp duty or loan limits that affects buyers, while the balance units chart and the recent transactions page update as sales continue and new caveats are lodged.
For a particular home, the Sales Concierge can confirm which stages have been reached and send the payment schedule with the price list. Showflat viewings are arranged by appointment through the Sales Concierge.
This article is general information as at the date shown and is not financial, legal or tax advice. Particulars of ELTA are from the developer’s published documents, statutory figures are as set out on this site’s financing pages, and distances are straight-line measurements on OneMap. Sources: the developer’s factsheet (31 December 2024), e-brochure (January 2025), floor plans and unit annexes; EdgeProp (preview, launch and top-out reports).